Posted by: eyespie1 | April 24, 2010

The Hospital programme update: 22nd April 2010

1. By May 2010: Will have completed 6 Great Crested Newt Surveys (on site now- have done 2 todate)

2. By June 2010: Reserved Matters Planning application Submission

3. October 2010: Work commences on the Swinemoor site

4. Construction completion date: December 2011

5. Hospital facility Operational: January 2012


Responses

  1. […] a great crested newt have been found on-site in October 2009, necessitating the commissioning of a survey now that should  have been carried out BEFORE applying for Planning […]


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Categories

%d bloggers like this: